Page 309 - 360.revista de Alta Velocidad - Nº 6
P. 309

The railway station as link of electromobilty

                                                             KEYNOTE

                                           Table 4: control and automation networks



                                                                                     The device maximum
                    Technology    Transmission medium        Transmission speed
                                                                                            distance
                      Konnex        1.TP0, 2.TP1, 3.PL100,   9600 bps, 3. 1.2 – 2.4 Kbps,   2. 1000 m, 3. 600 m
                                  4.PL132, 5.Ethernet 6.Radio      4. 2.4 Kbps
                     Lonworks    1. TP, 2. Power cord, 3. Radio,   1. 78 Kbps, 1. 1.28 Mbps,      1. 500 m – 2700 m
                                       4. Coaxial, 5.FO           3. 5.4 Mbps
                        X10              Power cord          60bps USA, 50bps Europe         185 m
                                                                                                  2

                      BacNet         Coaxial cable, TP, FO       1Mbps-100 Mbps     Con Ethernet sobre TP: 100 m

                        EIB        1.TP, 2. Power cord, 3.RF,   1. 9600 bps, 2.1200/2400 bps  1. 1000 m, 2. 600 m, 3.300 m
                                         4.Infrared
                        EHS          1. Power cord, 2.TP      1. 2.4 Kbps, 2. 48 Kbps

                      Batibus               TP                      4800 bps        200 m a 1500 m Depending on
                                                                                      the section of the cable
                       Cebus        TP, Power cord, Coaxial,        10 kbps         Depending on the characteris-
                                       Infrared Radio,                                tics of the environment
                       DALI               Cable par                                          200 m

                      Metasys              N2Bus                    9600 bps                 1219 m


                        SCP             Par de cable               <10000 ps


                      Zigbee              Wireless                20-250 Kbps              10 m – 75 m


                          2.7     Energy efficiency and quality of network

                   The set of power systems installed on micro intelligent network formed by the catenary, OURSES,
                   quality network and loads, distributed storage system, are intended to extract, modify, store,
                   and manage the electrical energy in the most efficient way possible, always ensuring the quality,
                   reliability, robustness, and security of electricity supply.
                   To do this, each of these systems incorporates control and management advanced algorithms
                   giving them independence and autonomy within the MSG, but at the same time they introduce
                   them  and  synchronized  with  the  rest  of the  electrical  infrastructure  that  surrounds them.
                   Looking for the efficiency and quality of whole from each of the parties in this way.
                   However,  not only electronic  systems  interact  with  each  other,  the  human  factor within  a
                   system that hosts the project is a variable to take into account. The decisions taken by the
                   owners of the vehicle will influence within the energy management of the micro network. Type
                   of refills, time and simultaneity of the same in the near future transfer of power by the vehicle
                   (vehicle to grid (V2G)), etc., are heavy weight variables in the system. That is why there must
                   be a proper coordination between these and power systems distributed in the MSG.

                   On the other hand, the manager-operator system may interrupt the autonomy of the system
                   during maintenance, alarm signals, incidents on the line, etc. These operations and decisions