                          2.3     Background: Ferrolinera 1.0 and 2.0

                   The Ferrolinera 1.0 project, now completed, must encompass as a first pilot project to analyze
                   possible problems that may occur in this type of cargo operations. It has been tested in the
                   laboratory of energy of ADIF, four scenarios of an electric vehicle charging. This has been used
                   a commercial charger, although different own electronic equipment enabling connection to the
                   electric rail system has been developed.
                   The Ferrolinera 2.0 project, currently under development, is based on the above results and aims to
                   continue working with a commercial but already plugged charger out of the controlled environment,
                   such as the laboratory of energy of ADIF. Precisely, the objective is to install a Ferrolinera connected
                   to the electric rail system (catenary) on the AVE station Maria Zambrano (Málaga).

                              2.3.1      Project 1.0 Ferrolinera: stage 1
                   Consider the power of the Ferrolinera from a reducing transformer of a distribution line voltage.
                   Does not require additional specific equipment.