High Speed Rail in Spain - a statement from a foreign expert




                   The  interchange  conditions  for  Sevilla  could  be  optimized,  if  a  platform  with  an  European
                   standard track at the one side (track 4) and a track with Iberian gauge at the other side (track
                   5) could be realized. This idea is shown in figure 7. This sketch was designed before seeing
                   Sevilla station in practice. The platform between track 6 (1435 mm gauge) and track 7 (1668
                   mm gauge is the most important platform in Sevilla station.




                   Córdoba
                   The interchange situation in Córdoba is very convenient for passenger change. It is assumed
                   that the third train can run in the track of the first train. A 4 minutes space between these two
                   trains contains already 1 minute recovery time.












































                                            Figure 8. Track occupation diagram for Córdoba station

















                   International Congress on High-speed Rail: Technologies and Long Term Impacts - Ciudad Real (Spain) - 25th anniversary Madrid-Sevilla corridor  499
   496   497   498   499   500   501   502   503   504   505   506