Page 200 - 360.revista de Alta Velocidad - Nº 6
P. 200

Fernández-Ges, Andrés.




                 2015 and the economic crisis, the rest of the Digital Mile project has not been yet developed
                 and it does not seem that this project will happen.



































                                  Fig 27. Display of uses and public facilities in Digital Mile. Source: City Council.


                 17.  Selling the first real estate plot


                 To sell the first parcel was necessary to change the planning of the area, extracting one parcel
                 and classifying as a urban soil. Once separated from the area AC-44, the parcel could be sold.
                 Selling this first parcel was crucial to make possible the operation to start. A bid was launched
                 in January 2006. In this first competition, the real estate developers were asked to make an
                 economic offer and an architectural design, being more valuable the economic offer, although
                 the design proposed should have a minimum quality.
                 The parcel had 285 dwellings and a flexible design that could reach thirty floors. It was sold by 82
                 million Euros, the highest price paid ever in the city. to NOZAR, a national real estate company.
                 There was another offer with a higher rated architectural design, but the price difference with
                 the second bid was unbeatable. Nevertheless, the winning tower was very elegant with good
                 quality design.

                 The neighborhood became worried with the danger of gentrification accusing the administrations
                 and ZAV to be speculative with the public land. Nevertheless, this situation encouraged to the
                 administrative entities to develop more works and infrastructures.

                 To build the design was necessary to do a special plan regulating the architectural volumes and
                 urbanization of the area. The administrative procedures took a long time to be approved and
                 when the company was able to get the license the economic crisis had arrived and the company
                 could not start building.